CM Maryam Sets March 2027 Deadline for Mass Transit Projects

CM Maryam Sets March 2027 Deadline for Mass Transit Projects
NewsCM Maryam Nawaz

Quick Answer

Punjab Chief Minister Maryam Nawaz has directed officials to complete the Faisalabad and Gujranwala mass transit projects by March 2027. She ordered construction work in three shifts to meet the deadline. The 31.5-kilometre Gujranwala Yellow Line will have 25 stations, including two underground stations.

Punjab Chief Minister Maryam Nawaz reviewed the progress of the Faisalabad and Gujranwala mass transit projects during a special meeting in Lahore.

Officials gave her a detailed briefing about the work completed so far. The chief minister also checked the construction progress through drone footage.

She directed the departments concerned to speed up work and complete both projects within the given deadline.

Faisalabad and Gujranwala Mass Transit Projects Overview

Detail

Information

Projects

Faisalabad and Gujranwala Mass Transit Systems

Gujranwala Project

Yellow Line

Gujranwala Route Length

31.5 kilometres

Total Stations

25

Underground Stations

2

Underpasses

12

Service Road

35 kilometres

Completion Deadline

March 2027

Work Schedule

Three shifts

Supervising Authority

Punjab Government

Work to Continue in Three Shifts

CM Maryam directed officials to arrange construction work in three shifts. The decision has been taken to increase the pace of work and complete the projects by March 2027.

The departments working on roads, drainage, electricity and utility lines will need to coordinate their work. This will help prevent delays caused by one department waiting for another to finish its part.

The chief minister also directed officials to regularly check the construction progress.

Gujranwala Yellow Line Route

The Gujranwala Yellow Line will cover a route of 31.5 kilometres. It is planned to provide an organized public transport service to people travelling across the city.

The project will have 25 stations, including two underground stations. These stations will provide passengers with access to the mass transit service from different parts of Gujranwala.

The project should be called the Gujranwala Yellow Line. The use of “Blue Line” in some reports appears to be an error because official and other published project details identify it as the Yellow Line.

Underpasses and Service Road Planned

The Gujranwala Yellow Line project will include 12 underpasses and a 35-kilometre service road.

Signal-free U-turns will also be built along the route. These road improvements are planned to manage traffic near the mass transit corridor and make daily travel easier.

The service road will help local traffic move without entering the main transit route.

One-Third of Gujranwala Project Nears Completion

Officials informed the meeting that nearly one-third of the Gujranwala Yellow Line work is close to completion.

A total of 1,233 electricity poles and 552 transformers have been installed. This work is necessary to support the power system and complete construction along the route.

Further work on stations, roads, underpasses and other facilities is continuing.

Drainage System Work Reaches 40 Percent

A 62-kilometre drainage system is being constructed as part of the Gujranwala project. According to the briefing, around 40 percent of this work has been completed.

A proper drainage system will help remove rainwater from roads and areas near the transit corridor. It can also reduce the risk of water collecting around stations, underpasses and service roads.

New Utility Lines for Gujranwala

Several utility lines will be installed during the construction of the Yellow Line.

The planned work includes:

  • 15,000 feet of sewerage lines.

  • 12,000 feet of water supply lines.

  • 11,000 feet of gas pipelines.

Completing this work during the main construction can reduce the need to dig up newly built roads later.

Progress on Faisalabad Mass Transit System

Officials also presented an update on the Faisalabad Mass Transit System.

According to the briefing:

  • 1,835 trees have been replanted.

  • 15 kilometres of gas pipelines have been laid.

  • 12 bus stops have been constructed.

These works are part of the preparations for the city’s mass transit system.

Trees Replanted During Construction

The meeting was informed that 1,835 trees affected by the Faisalabad project had been replanted.

Moving and replanting trees can reduce the environmental impact of construction. The condition of these trees will need regular checks to make sure they survive after being moved.

Expected Benefits for Citizens

The two projects are expected to improve public transport in Faisalabad and Gujranwala.

Once completed, they may provide the following benefits:

  • Easier daily travel.

  • Better access to public transport.

  • Reduced pressure on busy roads.

  • Improved traffic flow.

  • Safer bus stops and stations.

  • More organized transport routes.

  • Better connections between important city areas.

The projects can be especially useful for students, workers and other passengers who depend on public transport.

CM Maryam Orders Timely Completion

Maryam Nawaz said she was aware of the problems faced by residents during construction. She directed officials to complete the work within the assigned time.

Large construction projects can cause road closures, traffic delays, dust and changes to local routes. The departments concerned will need to manage these issues while continuing work in three shifts.

Regular progress checks will also be important to meet the March 2027 deadline.

What Residents Should Know

Residents living or travelling near the project routes may face temporary traffic changes during construction.

They should follow:

  • Official traffic updates.

  • Temporary route signs.

  • Instructions issued by local authorities.

  • Announcements about road closures and diversions.

Project dates and traffic plans may change as construction continues. Residents should rely on updates from the Punjab government and relevant local departments.

Frequently Asked Questions

1. When will the Faisalabad and Gujranwala mass transit projects be completed?

CM Maryam Nawaz has directed officials to complete both projects by March 2027.

2. How long is the Gujranwala Yellow Line?

The Gujranwala Yellow Line will cover a total distance of 31.5 kilometres.

3. How many stations will the Gujranwala Yellow Line have?

The project will have 25 stations, including two underground stations.

4. What work has been completed on the Faisalabad Mass Transit System?

So far, 1,835 trees have been replanted, 15 kilometres of gas pipelines have been laid and 12 bus stops have been constructed.

5. Why has CM Maryam ordered work in three shifts?

The three-shift schedule aims to speed up construction and complete both mass transit projects within the March 2027 deadline.

Article Details

Category: News

Published:

Updated:

Author: Rabia

More Stories

Continue Reading

View Category

Stay Up To Date On The Latest News

By pressing the subscribe button, you confirm that you have read our privacy policy.